“We ate all the meat; there are only bones to chew on now”

Comimos toda la carne; sólo nos quedan los huesos” (we ate all the meat; there are only bones to chew on now”, said Luis Romero of CONASA (the water and sanitation policy making body in Honduras), in response to the graphs below, when we presented these as part of the sharing of the results of the life-cycle costs analysis in Honduras.

The first graph shows the average per capita investment costs (based on 114 water supply projects), in relation to the population size. As can be seen these per capita costs are much higher in dispersed rural setting (between 0 and 200 inhabitants) than in more nucleated rural settings (more than 200 inhabitants). This is not a surprising figure. The costs of development of water infrastructure are not linear with the population a water system serves. There are many fixed costs, which become relatively big in smaller systems than in bigger ones. Also economies of scale can be obtained in for example procurement and transport of materials for bigger systems than for smaller ones which are typically located further away and are harder to reach. A similar relation was found for latrine projects: average per capita expenditure was 133 US$/p in dispersed rural settlements and 85 US$/p in bigger nucleated settlements (all being pour-flush latrines).

Graph1

Graph 1: Average per capita investment costs in relation to population size

Luis Romero’s remark referred to the fact that the country has enjoyed the relatively nice part:  covering the nucleated settlements which are cheaper to reach. Now there will be a hard bone to chew on: covering the estimated 10.000 small hamlets at those very high investment costs. The formal coverage statistics don’t differentiate the degree of coverage between the dispersed and nucleated rural settlements. But, the sector experts all agree that the nucleated settlements are largely covered – at most there may be need for extensions as communities grow. But where coverage is lowest is in dispersed rural areas.

The second graph shows an even harder bone to chew on. It provides a histogram of the per capita investment costs of 40 capital maintenance projects. These are projects, that consist of the partial or full replacement of assets. They may range from the replacement of a main line to the full replacement of the distribution network, or even building a new water system on old one that has reached the end of its life span.

Graph2

Graph 2: Histogram of per capita investments costs of capital maintenance projects

The graph shows that almost half of these projects were relatively small in size at low per capita costs, of up to 50 US$/person. These typically were projects that consisted of replacement of one critical component, such as a main line, an intake structure or a storage tank. Communities covered on average 12% of the costs of these works; the rest was paid out of external funds, mainly grants and loans by donors and development banks to the government of Honduras. Supposedly, communities are responsible for covering such kind of capital maintenance works out of the tariffs they raise. This graph provides again evidence for the fact that this is clearly not happening. A typical rural water tariff is about 2 US$/family month. If we assume that half of this is amount is set aside for saving and the other half to cover running operational costs (e.g. for chlorination and paying a remuneration to the village plumber), than on average 12 US$/family, or 3 US$/person can be saved on a yearly basis. A replacement that costs 50 US$/capita can only be afforded every 16 years. In reality, many components have much shorter life spans. Only in the most optimistic scenarios can communities’ savings cover these costs. And the graph shows that in fact, the government through its donor funds, steps in to pay the bill. In addition, there is a number of projects that had much higher per capita costs, these being systems that were almost completely replaced.

This is also the graph that shows how the future of the Honduran sector investments may look like. As most nucleated settlements are covered, many will need periodic replacement of critical assets, either big or small. Eduardo Sánchez, programme manager at a rural water supply programme, illustrated this. A recent call for proposals of that programme for investment projects, yielded 32 proposals from municipalities covered by the programme, many of which were for capital maintenance projects. There are simply few uncovered nucleated settlements where new systems need to be built – but many need replacement works, big or small.

For the rural WASH sector this poses a very critical question on where to invest: in extending coverage to all the small dispersed settlements, at high per capita costs, or in co-financing capital replacement works in villages already covered but which simply have not been able to raise sufficient funds to undertake such works themselves.

This led Luis Romero to make another important remark: “We need to develop a very clear policy on these kinds of capital maintenance projects”. He explained that below a certain total and per capita costs, such projects should not be done by the public sector, or at most only through a combination of community and municipal contributions. Only in that way, would the government be able to extend services to the unserved in dispersed settings, while at the same time give the signal to communities that they need to save up for replacements and not rely on the government to step in, particularly if the repairs fall within their capacity to pay. This will above all require developing much clearer definition of what are minor replacements that can be done by the community, and which ones are major, for which it would be justified to have government contributions. This would need to be applied in a consistent manner as well.

Such a policy may be developed on the basis of the kinds of unit costs ranges we are identifying. Enforcing it will be more complicated, as it requires consistent application by all, both government and NGOs. And even then, there may be all kinds of political reasons for the government to jump in the next time the main line breaks, or a tank needs to be replaced. For the years to come it means chewing both the bone of reaching everyone, indeed everyone, and ensuring that the ones who are reached have services that last forever.

Advertisements

7 comments on ““We ate all the meat; there are only bones to chew on now”

  1. Great insight and hard data showing the need for improved financial accountability and investment. Hope to see better policies come out of your workshop, Stef!

  2. Reblogged this on Rural Water Supply Network – Blog and commented:
    analysis of life cycle costs in Honduras

  3. “This will above all require developing much clearer definition of what are minor replacements that can be done by the community, and which ones are major, for which it would be justified to have government contributions.” This sentence, and idea, jumped out at me given our work in Uganda with community WASH projects. The WatSan Committees are generally responsible for maintenance and repairs that cost under UGX300,000 (~USD 115) and then the government is supposed to assist. However, our experience in practice is that this rarely happens and the water systems go into disrepair. I look forward to learning how CONASA proceeds to implement policy around this and how it is implemented and monitored. This is a great blog and discussion. Leslie Moreland for WaterCan

    • Dear Leslie,
      That will indeed tbe the tricky thing. It is relatively easy to put forward such a cut-off line, under which communities are supposed to cover the full costs, and one above which Government would step in. One could even think of all kinds of intermediate cut-off lines, e.g. if it is between 115-300 US$, it would be financed 50-50 between communities and govt and above that, it would be fully financed by govt. Or, one could even differentiate it between size of communities. a bigger community should be able to take care of bigger repairs than a small one. One can developed beautiful calculations around that. But enforcement of that will be key, particularly to avoid that govt takes up a paternalistic role and funds relatively small repairs (at the expense of probably more urgent big ones). That could also be done by for example, defining it clearly in regulatory frameworks or frameworks for public spending. But still the key issue will remain how to enforce the payment of the relatively bigger capital maintenance works. Maybe by avoiding the smaller repairs funded out of public funds, the local govt will have more funds available for the more urgent bigger works. this would be one way around it. There is currently also all kinds of research into out-of-the-box mechanisms with insurance schemes, pooled funds etc. I am very curious whether and how those work, and I would encourage readers of this blog to experiment with those and let us know the results. But in my view the first step is indeed what the govt of Uganda has done, and that is trying to define what is major and minor repair and who is responsible for what. once that is done the specific enforcement rules need to be developed and financing mechanisms established. this will not be an easy task, neither in Honduras, nor in Uganda, or elsewhere but i feel it is the route we need to follow to start addressing the issue of capital maintenance
      Best regards,

      Stef Smits

  4. In Nepal, the Rural Water Supply and Sanitation Fund Development Board (RWSSFDB) is piloting a micro-insurance scheme for rural water systems. The aim is to have 1,000 schemes insured by the end of this year. For a small monthly premium – “less than the cost of a cup of tea” – households can insure their water systems against the risks of natural disasters. So far the RWSSFDB has only found one local commercial insurance company prepared to offer an insurance package covering earthquakes, landslides, floods and fire. (Read more in the 2011 RWSSFDB Annual Report, p. 33 – http://www.rwss.org/document/reports/english/RWSSFDB_AR_ENGLISH.pdf)

    I met Ramesh Kumar Sharma, International Steering Committee Member of the RWSSFDB, last week at the Water Integrity Forum in Delft. He told me that several other insurance companies had been approached but most found the amounts involved too small to be commercially attractive. Mr. Sharma said the companies were really only interested if they could sell life insurance as well – suggesting than some form of combined life / water system insurance might be an option.

  5. Very interesting and highlights a few themes that are of particularly interest to me. The biggest one is coordination – if there is indeed a policy of no more external funds for certain repairs, that takes away the low-hanging fruit of “rehabilitations” that NGOs like to put in front of donors. If communities hear that their neighbors are getting free repairs while they have to pay for their own will cause conflict.

    However, it’s not just about communities paying for the real costs of water services – it’s also about the water service providers having access to technical support or a network of peers so they can actually use the funds efficiently and effectively (and perhaps avoid the need for some of the more expensive repairs).

    Should NGOs & donors stop doing anything related to infrastructure and start supporting strong local water services management and national regulation and monitoring?

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: